Mildas Fair


Temporary building - fair place "Green Market"

 

Address: Ernesta Birznieka - Upīša iela 2, Riga

Construction area: 1618 m2

Construction period: December 1st,2009- March 3rd 2010

 

Client:  Jumāras īpašums LLC

Architct: Jānis Norde

Project designer:  "Sarma un Norde" Architectural Bureau

Cost: LVL 285 000

 

 
Tallink Hotel Riga


Address: Elizabetes street 24/26, Riga

Total area (area to be built): 11 021,90 m2

Construction period: 2008-2010

Architect: Statio Architecture LLC; manager of the construction project:  architect Uldis Mazais

Author of the hotel interior design: „M. Pressi Arhitektuuriburoo” LLC; Head Designer Meelis Press (Estonia).

Investments: LVL 21,06 million .

 

In 2008, Merks commenced the construction of the seven-story hotel Tallink Hotel Riga at Elizabetes iela 24/2. Construction was completed on 31 March 2010.

There were built 256 rooms, three elevators, an underground car park, beauty salon and recreational complex, a lobby bar, a restaurant and 6 conference rooms in the hotel.

During the construction process, the historic façade of the building designed by the renowned architect K. Felsko in 1897 is preserved. The entirety of the whole building, characteristic to Riga historic centre, has been retained in the dimensions of the hotel.

The hotel was opened for operation in April 15, 2010.

 
Reconstruction and Extension of Water-main and Sewerage System in Carnikava


Client: Carnikava municipality

Construction period: 2008.-2010.

Cost: LVL 3,7 million

 

 Agreement for "Renovation anf extension of water-main and sewerage system in Carnikava" was concluded with "Merks" Ltd. on 2 October, 2008.

 

By entering into contract a modern water supply system was reconstructed in  length of 3.2 km and extension of water supply and sewerage system in length of 1,5 km were reconstructed. As well as sewerage nets were reconstructed and extended in the length of 7.69km.

Project was financed by Cohesion Fund of European Union, LAtvian State and Municipality of Carnikava.

 

 
Psychoneurological Hospital in Strenči

Construction of the emergency care building, including admissions and administrative sections. Reconstruction of the existing building of psycho-tubercular patients’ ward.



Address: Valkas iela 11, Strenči

Type of construction work: new construction, reconstruction

Client: Psychoneurological hospital in Strenči

Project designer: Ozola & Bula LLC Architectural Bureau

Construction period: March 2009-September 2009

Total area: 3 613,9 m2

Cost: LVL 2.25 million

 